Project Management
Create a testing plan
Once the testing plan is ready, your team can:
Test the user interfaces
Test the database
Test the network
Write the documentation first draft
When the user interface tests are complete, you can:
Perform user testing—enlist some users to test the user interface
When the database and network testing are complete, you can:
Perform integration testing—network with the database
When the user testing of the user interface and the database testing are complete, you can:
Perform integration testing—database, network, and user interface
When all integration testing and user testing are complete, you can:
Perform system testing
Then you can:
Review and revise documentation
After all other tasks are complete, you can:
Obtain management approval
Duration estimates for the tasks:
a.3 days
b.10 days
c.6 days
d.7 days
e.20 days
f.5 days
g.3 days
h.2 days
i.8 days
j.4 days
k.5 days